With a nice easing into Spring, we were able to get an early jump on the prep and excavation. Today, we formed the footings and the inspector came by and gave us the go ahead to pour.
The block wall is done and Thom has started his waterproofing process... weeping tile around the footing, covered by a healthy 12" of gravel (after the inspector was by to check); parged block wall, rounded at the bottom to encourage water away from the footings; bitumen painted and then a locking membrane pressed in and another layer of bitumen painted over; blue skin on the corners where new joins to old, and finally, a layer of plastic dimpled membrane to provide an air and drainage layer for water that makes it inside to the wall.